One-block long closures of Chadbourne Street begin Monday for sewer main replacement

Intersections will be also be closed as the respective streets are being worked on, beginning with 22nd and 23rd street intersections.
Credit: COSA

SAN ANGELO, Texas — Beginning Monday, Aug. 16, one-block sections of Chadbourne Street will be closed as work to replace sewer mains progresses north from 22nd to 43rd streets.

Intersections will be also be closed as the respective streets are being worked on, beginning with the 22nd and 23rd street intersections.

Vehicle detours will be marked in areas where there is construction occurring.

Each block closure is expected to last approximately a week, with the final completion date around late November, pending any potential weather delays.

This work is part of the North Chadbourne Sewer Main Replacement Project that began several weeks ago.

For more information on City street projects visit cosatx.us/Streets.